1. First wet the base surface of the wall with clean water, and only when there is no clear water on the surface can it be used as a binder.
2. Confirm that there is no clear water on the base surface, batch scraping special artificial stone adhesive (strip shape/full batch scraping) thickness of more than 3mm, the same practice on the back of the stone, the thickness is 2-3mm, and then paste the stone.
3. After pasting the stone within the specified time (according to the requirements of the adhesive product instructions), it is necessary to twist slightly and rub the stone up and down or gently beat it with a mallet to make the stone fit closely with the adhesive. (For wall laying, the construction team can also add copper wire to fix it according to the design requirements).
4. Correct the seam between the horizontal and the adjacent plate, and pay attention to the seam between the stones of 2mm or more.
5. Preliminary cleaning of the dirt attached to the surface of the plate, the pasted stone 3 days after (according to the instructions for the use of special artificial stone adhesive) can be cleared and seam treatment, caulking should use artificial stone special caulk.
6. Clean after caulking treatment (cannot use acid-containing and alkaline cleaning agents, it is recommended to use special artificial stone cleaning agents) caulks and dirt attached to the surface of the plate.
7. After the stone is laid, the film is torn apart after acceptance and cleaning.
8. It is recommended not to use traditional stone wet hanging construction.